Commercial New Build of 3 units



Project Responsibility: Principal Contractor
Location: Gateshead
Project Completion: 19 weeks
Project Description:

The build incorporated a ground floor retail store with two residential apartments above. The project was completed within the agreed timescale despite extra variation to the ground works. The foundations had to be strengthened with steel cantilever systems and the neighbouring property had to be considerably underpinned to stabilise it. All the ground works, drainage system, specialist concrete floor systems, traditional block and brick superstructure, and mechanical and electrical systems with complete internal works and fit out were completed in 19 weeks.

CASE STUDY